LAR-256: Walls New 10' x 60' in-ground vinyl lap pool Dig Walls Floor Liner Plumbing/Equipment Final Back Wall Panel Layout After digging and tamping, we begin laying out where all the wall panels are going to go. Connecting panels We bolt the panels together first and then install the step panels. Squaring and leveling As soon as walls are bolted together, we square the walls. We then brace the walls and use the braces to level the walls into place. Pouring Bond Beam During the bond beam (footing) pour, we place sono tubes that will be eventually filled with concrete to support sub deck.
After digging and tamping, we begin laying out where all the wall panels are going to go.
We bolt the panels together first and then install the step panels.
As soon as walls are bolted together, we square the walls. We then brace the walls and use the braces to level the walls into place.
During the bond beam (footing) pour, we place sono tubes that will be eventually filled with concrete to support sub deck.